7th Street Update

7th Street Update
7th Street Update

Week Ending March 27, 2021: After the precipitation early in the week, Morgan Brothers Construction continued removing sections of pavement throughout the end of the week for Phase II of the project.

Looking ahead: Morgan Brothers Construction will continue removals on this Phase of the project. Early this week they will be placing aggregate millings on top of geofabric for the base work. Concrete …